LETTER: California Bullet Train Contractor Says Project Could Miss Key 2022 Federal Deadline

Los Angeles Times-


One of the state’s top bullet train contractors has sent a scorching 36-page letter to California high-speed rail officials, contradicting state claims that the line’s construction pace is on target and warning the project could miss a key 2022 federal deadline.

The letter, obtained by The Times, alleges that a multitude of problems have remained unresolved for years, including rapid turnover of state officials, continuing delays in obtaining land for the rail and the state’s failure to secure agreements with outside parties, including utilities and freight railroads. The delays will result in idled work sites and layoffs of field workers, says the letter, by construction giant Tutor Perini.

As of mid-November, construction teams can not build on more than 500 parcels in the Fresno area because the California High Speed Rail Authority still lacks possession or proper documentation, according to the Jan. 4 letter. The company has completed all the work that could be done efficiently and as a result is now operating at other sites at a slower pace.

Read More

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: